DCDC PROGRESS PHOTOS FOR THE MONTH OF JULY (ADMIN WORKS) @ THIRD FLOOR LEVEL – July 28, 2022

1. Completed installation of wooden doors @ patient rooms and semi private rooms including CR and pipe chase. ‘

2. Completed installation of wooden doors @ PEDIA,STROKE,O.B AND SURGERY WARDS including CR and pipe chase.