UCCPI Update – April 28, 2022

Installed cable trays for outdoor unit at roof deck gridlines 8-12/A-H 2. Arranged and terminated wires at roof deck GL 2-3/D-E 3. Arranged and terminated wires at ee room fourth floor 4. Arranged and terminated wires at ee room third floor 5. Arranged and terminated wires at ee room second floor 6. Arranged and terminated

Read More
Brun Update April 28,2022

1. continue installation of mainline copper pipe from riser to outdoor unit connections at roofdeck GL 7 – 8 / D – H. Work 95% progress at riser 2 2. fixing of additional steel brackets to fit with the outdoor units in preparation to the installation of outdoor units at Third floor patient’s room GL