DCDC DAILY ACTIVITY MASONRY WORKS APRIL 28,2022

1. Plastering of zocalo @ skylight area second floor level.

2. Plastering green area plant box @ main facade ground floor level.

3. On going concrete topping @ roof deck level

4. On going plastering and topping of step and riser @ fire escape 2&3 from ground floor level up to second floor level.

5. On going application of skimcoat @ library/ chief nurse and custodian fourth floor level.

6. On going installation of granite cladding @ elevator ground floor level.