1. Installation of wooden doors jambs schedule D-1 @ corridor 1, folk lounge,MICU and PICU second floor level.
2. On going concreting of two sides and header for wooden doors jambs @ accounting office fourth floor level.
3. Installation of chandelier bracket @ main lobby ground floor level.
4. On going concrete topping for pipe chase @ patient rooms 20-25 fourth floor level.