DCDC DAILY ACTIVITY MASONRY WORKS – APRIL 18, 2022
1. On going installation of stair tiles @ stair-1 from third floor level up to mid landing fourth floor level. […]
1. On going installation of stair tiles @ stair-1 from third floor level up to mid landing fourth floor level. […]
1. On going installation of ceilings framing, hangers and t – tanners @ auditorium area Third floor level.
1. On going installation of stairs tiles @ stair-1 from lower ground floor level up to fourth floor level. 2.
1. On going application of final color second coating and patching @ open above areas third floor level. 2. On