UCCPI ELECTRICAL ACTIVITIES (FEB 04, 2022)
1. Installation of pvc pipes, utility boxes, and wires for additional power supply of medical gas at fourth floor GL […]
blog
1. Installation of pvc pipes, utility boxes, and wires for additional power supply of medical gas at fourth floor GL […]
1. Ongoing lay-out and chipping & grinding for 2-Gas zone valve box and area alarm @ 2F-Corridor GL G-H 2.
1. On going alignment of sprinkler heads at acoustic ceiling @upper ground floor 2. On going fabrication of flanged tee
Roughing installation of CATV @ 4th floor and lower ground floor
Layout & Installation of copper pipes from indoor units to outdoor units locations at roofdeck parapet walls, GL 2 –
Completion of rubber insulations on the installed copper pipes from door units to outdoor units locations at 4th floor GL