DCDC DAILY ACTIVITY PAINTING WORKS – April 18, 2022

1. Erection of scaffolding for the retouching of exterior painting @ left side elevation exterior wall partition.

2. On going application of final color first coating and patching @ stair -1 ground floor level up to fourth floor.

3. On going application of boral for ceiling @ main lobby ground floor level.

4. On going application of boral for ceiling @ fourth floor level.