  • DCDC DAILY ACTIVITY PAINTING WORKS – April 18, 2022

    1. Erection of scaffolding for the retouching of exterior painting @ left side elevation exterior wall partition. 2. On going application of final color first coating and patching @ stair -1 ground floor level up to fourth floor. 3. On going application of boral for ceiling @ main lobby ground floor level. 4. On going

    Read More

  • DCDC Daily Activity Admin Work – APRIL 8, 2022

    1.On going installation of roofing @ STP equipment room. 2. Concrete topping @ patient rooms 1-7 pipe chase third floor level. 3. Concrete topping@ semi private room 1-6 Third floor level. 4. Concrete topping@ pedia ward 1 and 2 and O/B ward 1 and 2 third floor level. 5. Installation of wooden doors jambs @

    Read More

  • Installation of Signage by Art Yard – April 22, 2022