1.Installed vinyl@ground floor hallway in between clinic rooms and dialysis room. 2.installed vinyl @ ground floor hallway in between laboratory…
1. On going installation of ceiling framing @ canteen, food preparation lower ground floor level. 2. Completion for the installation…
1. Installation of wooden doors jambs schedule D-1 @ corridor 1, folk lounge,MICU and PICU second floor level. 2. On…
1. Plastering of zocalo @ skylight area second floor level. 2. Plastering green area plant box @ main facade ground…
Installed bedhead console unit @ 3F-Patient rooms GL G-H/6-10
1. Erection of scaffolding for the retouching of exterior painting @ left side elevation exterior wall partition. 2. On going…
1.On going installation of roofing @ STP equipment room. 2. Concrete topping @ patient rooms 1-7 pipe chase third floor…