UCCPI ELECTRICAL PROGRESS PHOTOS AS OF THIS MONTH – July 28, 2022
1. Installed 120×30 lighting fixtures at second floor corridor-1 and corridor-22. Installed 120×30 lighting fixtures at upper ground floor corridor-1
Uncategorized
DCDC PROGRESS PHOTOS FOR THE MONTH OF JULY (PAINTING WORKS) @ GROUND FLOOR LEVEL – July 28, 2022
1.Application of final color @ corridor 1 & 2, laboratory waiting area, radiology hallway, main lobby, pharmacy, minor O.R and
Uncategorized
DCDC PROGRESS PHOTOS FOR THE MONTH OF JULY (PAINTING WORKS) @ SECOND FLOOR LEVEL – July 28, 2022
1. Application of aqua epoxy paint final color second coating for O.R clean/dirty,CS 1&2 , DELIVERY 1. 2. Application of
Uncategorized
DCDC PROGRESS PHOTOS FOR THE MONTH OF JULY (PAINTING WORKS) @ THIRD FLOOR LEVEL – July 28, 2022
1. Application of final color corridor -1, corridor 2 and service elevator lobby hallway and nurse station. 2. Application of