Spurway Update April 28, 2022
1.Installed vinyl@ground floor hallway in between clinic rooms and dialysis room. 2.installed vinyl @ ground floor hallway in between laboratory and dialysis room.
Read More1.Installed vinyl@ground floor hallway in between clinic rooms and dialysis room. 2.installed vinyl @ ground floor hallway in between laboratory and dialysis room.
Read More1. On going installation of ceiling framing @ canteen, food preparation lower ground floor level. 2. Completion for the installation of t tanners for acoustic ceiling @ Laboratory area ground floor level. 3. On going installation of ceiling framing @ auditorium area Third floor level.
Read More1. Installation of wooden doors jambs schedule D-1 @ corridor 1, folk lounge,MICU and PICU second floor level. 2. On going concreting of two sides and header for wooden doors jambs @ accounting office fourth floor level. 3. Installation of chandelier bracket @ main lobby ground floor level. 4. On going concrete topping for pipe
Read More1. Plastering of zocalo @ skylight area second floor level. 2. Plastering green area plant box @ main facade ground floor level. 3. On going concrete topping @ roof deck level 4. On going plastering and topping of step and riser @ fire escape 2&3 from ground floor level up to second floor level. 5.
Read MoreInstalled bedhead console unit @ 3F-Patient rooms GL G-H/6-10
Read More1. Erection of scaffolding for the retouching of exterior painting @ left side elevation exterior wall partition. 2. On going application of final color first coating and patching @ stair -1 ground floor level up to fourth floor. 3. On going application of boral for ceiling @ main lobby ground floor level. 4. On going
Read More1.On going installation of roofing @ STP equipment room. 2. Concrete topping @ patient rooms 1-7 pipe chase third floor level. 3. Concrete topping@ semi private room 1-6 Third floor level. 4. Concrete topping@ pedia ward 1 and 2 and O/B ward 1 and 2 third floor level. 5. Installation of wooden doors jambs @