DCDC PROGRESS PHOTOS FOR THE MONTH OF JULY (PAINTING WORKS) @ FOURTH FLOOR LEVEL – July 28, 2022
1. Application of final color @ administration offices hallway/corridor 1, corridor 2, chief doctors and VIP OFFICES.
1. Application of final color @ administration offices hallway/corridor 1, corridor 2, chief doctors and VIP OFFICES.
1. Application of final color and rectification of uneven concrete surfaces @ front elevation and Left side elevation above stone
1. Installation of ceiling framing, dropping and ficem board @ emergency entrance and drop off area.
1. Installation of WPC (wood plastic composite) for wall cladding @ elevator lobby second floor is completed. 2. Installation of
1. Completed plastering and topping @ fire escape 2&3 from lower ground floor level up to roof deck level. 2.
1. On going installation of floor tiles @ lobby -1 lower ground floor level.
1. Completed installation of wooden doors @ patient rooms and semi private rooms including CR and pipe chase. ‘ 2.