DCDC PROGRESS PHOTOS FOR THE MONTH OF JULY (MASONRY WORKS) @ FIRE ESCAPE 1 – 4 – July 28, 2022

1. Completed plastering and topping @ fire escape 2&3 from lower ground floor level up to roof deck level.

2. On going plastering and topping @ fire escape 1&4 from second floor level up to roof deck level.